Loader pass-time benchmarks by phase

Published 2026-11-11 · CycleStudy Pro

Benchmarks give you a starting question: is this machine in the normal range? The figures below are working targets for hydraulic shovels and backhoes in typical open-pit conditions. Your own targets will move with machine size, material and bench geometry, so treat them as a first comparison, not a verdict.

PhaseTop rangeTargetInvestigate above
Dig8.5 to 10.5 s11.0 s or less14.0 s
Swing loaded5.5 to 7.0 s8.0 s or less10.5 s
Dump3.2 to 4.0 s4.5 s or less6.0 s
Swing empty5.0 to 6.0 s6.5 s or less8.5 s
Full pass24.0 to 27.5 s30.0 s or less38.0 s

What a slow phase tells you

From seconds to tonnes

Passes per hour is 3600 divided by the pass time. At 28 s that is about 129 passes; at 27 s about 133. One second per pass is roughly 3.7% of instantaneous digging capacity. Multiply by bucket payload to compare with your production target.

Measure the whole cycle too

Pass time shows operator skill. Gross cycle (dig to dig) shows how well the machine is supported. Report both, and keep delays separate from phase times so a waiting truck never counts against an operator.

Time your own cycles. CycleStudy Pro records loader and truck cycles offline and does this maths for you. Get the Android app or try the free calculators.